Site cut and fill in Berwick, day by day: what actually happens on your block
A standard single storey house pad on a flat or gently falling Berwick block takes two to three working days on site and costs $4,000 to $9,500. Day one is set out, strip and bulk cut. Day two is fill, lifts and compaction. Day three, if there is one, is trimming, batters and the spoil that would not fit on the last truck. Add a day for every extra 40 cubic metres of spoil, a day for rock, and up to a week of waiting if the weather turns.
Stage by stage, with the honest durations
This is a typical 100 to 150 square metre pad with about 20 to 40 cubic metres of cut. Times are for good conditions. Every stage below has a stall risk noted in the prose that follows, because the plan is easy and the ground is not.
| Stage | How long | What happens | What you need to do |
|---|---|---|---|
| 1. Before the machine arrives | 5 to 10 working days | Before You Dig Australia plans lodged, permits confirmed, deposit paid, surveyor or set out booked, crushed rock and tippers scheduled, weather window picked. | Clear the site, confirm your boundary pegs, let the neighbours know the dates, arrange somewhere to park. |
| 2. Float on | 30 to 60 min, from 6:30am | Float truck unloads the excavator on the street or the nature strip. Site fenced or taped, signage up, safety walk around. | Keep 12 to 15 metres of kerb clear out front. Move both cars off the driveway the night before. |
| 3. Set out and topsoil strip | 2 to 4 hours, day 1 | String lines and pegs to the plan, then 100mm to 300mm of topsoil stripped and either stockpiled for your garden or loaded out. | Nothing except stay clear. Dogs inside, kids inside. |
| 4. Bulk cut | 3 to 5 hours, day 1 | Cut down to design level on the high side, spoil loaded straight into tippers. Expect 4 to 10 truck movements in and out. | Expect noise and truck traffic. This is the loudest stage after hammering. |
| 5. Fill and compaction | Full day, day 2 | Fill placed in 100mm lifts, moisture conditioned with water, each lift rolled and checked before the next goes on. Nuclear densometer testing if specified. | Leave an outside tap accessible if we have asked for water. |
| 6. Trim, batter and drainage | 3 to 6 hours, day 2 or 3 | Final trim to plus or minus 25mm, batters cut back to a safe angle, ag drain or stormwater trench cut if it is in the scope. | Confirm where you want the stormwater to discharge if it is not on the plan. |
| 7. Clean up and sign off | 30 to 60 min | Street and driveway swept, spoil gone, levels recorded, dump dockets, before and after photos, handover folder. | Walk the site with us. Raise anything now, not in three weeks. |
| 8. Settlement check | 2 to 6 weeks later | Backfilled trenches and fill areas are checked after they have been through some rain. Minor topping up is normal. | Photograph anything that dips more than about 25mm and send it through. |
Indicative for a typical Berwick residential pad in 2026. Sloping blocks, tight access and rock all add time. Call 0485 813 822 for your actual programme.
Prepare for the crew: tick these off the week before
Every item here is something that has actually cost somebody machine time. Ticks save automatically in this browser, and the print button gives you a clean copy to stick on the fridge.
Access and parking
Clear the work area
Paperwork and services
People, pets and the house
Stop and call us if any of these are true
Want the programme for your block before you commit?
We will walk your site, measure the access and give you the actual day by day plan with the weather window we are aiming for.
What actually stalls a job
The programme above assumes nothing surprises us. Four things routinely do. Rock or floaters in the cut, which turns a five hour dig into a full day of hammering at $220 to $380 an hour on top of the machine rate. Deeper topsoil than expected, which is common on the old market garden ground around Cranbourne, Clyde and parts of Officer where there can be 300mm to 500mm of worked soil with no bearing value. A service that does not match the plans, which stops work immediately until the asset owner is contacted. And rain, which is the one nobody can argue with.
Access, parking, power and water
A 1.7 tonne mini excavator gets through a clear 900mm opening, a 3 tonne needs about 1.5 metres, and a 5 tonne wants 2.6 metres or the fence panel off. Measure at the narrowest point including the gate posts, not the gap in the fence line. Tipper trucks need 3.5 metres of width and 4.3 metres of clearance, and the low gum branch over your nature strip counts. If access is genuinely tight we can shuttle with a mini and a dingo, but it roughly doubles the hours, and the detail is on our tight access excavation page.
We bring our own fuel and we do not need your power. We do ask for an outside tap. Water is used for dust suppression, for moisture conditioning the fill so it will actually compact, and for washing wheels before trucks go back onto the street. If your tap is off or the connection is a garden hose fitting that leaks, tell us and we will bring a tank instead.
Noise, dust and smell
EPA Victoria’s normal construction hours are 7am to 6pm Monday to Friday and 7am to 1pm Saturday, with no work on Sundays or public holidays, and we work inside those hours. A 5 tonne excavator at 10 metres is loud enough to interrupt a video call. A rock hammer is another level again, so we book hammering into blocks and warn you the day before. Reversing beepers on the tippers are the thing neighbours notice most, and they are a legal requirement, so a heads up to the people either side is worth more than anything we can do about it.
Dust is managed with water. On dry February and March days we damp the pad and the haul path rather than let it blow. Smell is usually nothing, but if the block was a market garden or has organic fill in it, the first day of stripping can smell like a compost heap for a few hours. That fades once the topsoil is off and out.
Pets, kids and working from home
Dogs inside or at day care. Every operator has a story about a gate left open by a truck driver, and an excavator has blind spots you would not believe from the outside. Kids stay off the site including after hours, because a fresh cut with a 1.2 metre face is exactly the thing a nine year old wants to jump off. If you work from home, plan your calls around the first and last hour of the day, and expect the loudest window to be the bulk cut on day one.
Weather, and how we handle it
Casey gets roughly 700mm to 800mm of rain a year, concentrated between May and October. Reactive clay through Hallam, Endeavour Hills and Hampton Park cannot be compacted when it is saturated, because it will not hold density no matter how many passes the roller does. A day with more than about 15mm usually means two dry days before we can put the roller back on. Digging and trenching often continue in light rain, fill and compaction do not. We book clay heavy jobs into forecast dry runs and we will move your date rather than build you a pad that fails its test. If timing is flexible, the best time of year for earthworks in Casey is worth five minutes of your reading.
What a clean site looks like, and where the waste goes
At the end you should see a pad trimmed to within about 25mm of design, batters cut back to a safe angle, no loose windrows, no spoil left behind unless you asked for it, and a swept driveway and street. Mud tracked onto a Victorian road is the contractor’s problem to clean up, not the council’s and not yours. You get dump dockets, dated photos and the recorded levels in the handover folder.
Clean fill goes to a legitimate receiving site with a docket per load. Concrete, brick and rubble go to a recycler and come back into the industry as recycled crushed concrete, which is why that product is cheap and plentiful here. Green waste is separated. Anything asbestos suspect or contaminated is stopped, segregated and disposed of under EPA Victoria rules, which is slower and dearer, and we flag it the hour we see it rather than mixing it into the fill. If you want to know what settles afterwards and what does not, read backfill settlement and aftercare.
The honest bit: when the day should not go ahead
If the pad is under water, if the boundary pegs are missing, if there is unidentified sheeting in the ground, or if a service turns up that is not on the plans, we stop. A stopped day costs you a call out and a rescheduled crew. Pushing through costs you a failed compaction test, a service strike bill, or a pad in the wrong place. We would rather ring you at 7:05am and have an uncomfortable conversation than hand you a pad that has to come out. Related reading: what happens after a service strike and the signs of bad earthworks. Costs for each stage are in the 2026 pricing guide, and if you are still sizing the job, use the soil volume estimator.
What people ask before the machine turns up
How long does a site cut and fill take on a Berwick block?
What time will the crew arrive and how noisy is it?
How much access does the machine and truck need?
What happens if it rains during the job?
What should a clean site look like when the crew leaves?
Where does the spoil actually go?
Get your day by day programme and a fixed price
Send the block details and we will come back within one business day with the stages, the durations and a fixed quote.
Book the free site visit and we will measure the access for you
Berwick, Cranbourne, Narre Warren, Hampton Park, Endeavour Hills, Officer, Clyde and Hallam. Owner on site every job.